Estimator primitive
In gate-folding ZNE, why can an ideal gate U be replaced by the execution sequence U, U†, U?
A
The sequence cancels all physical hardware error exactly.
B
The ideal operation is still U, while extra noisy operations can increase the effective noise.
C
The sequence changes which observable is mathematically requested.
D
The sequence acts as identity and makes the circuit longer without the intended gate.